UAH will implement Uniform Guidance Procurement Standards for purchases on Sponsored Programs starting October 1, 2018, in accordance with government regulations CRR 200.317-326. The primary goals of the procurement standard are:
- Increase reuse of existing equipment and supplies
- Increase competition when purchasing equipment and supplies
- Minimize sole source purchases
- Purchases must be reasonable, allocable, and allowable
- Cost Allowability Guide can be found here
Micro Threshold
| Micro Threshold | Definition | Current UAH Policy | Recommendation to ensure UG Compliance |
|
|
|
|
Simplified Acquisitions
| Simplified Acquisitions | Definition | Current UAH Policy | Recommendation to ensure UG Compliance |
|
|
|
|
Complex Acquisitions: Sealed Bids
| Complex Acquisitions: Sealed Bids | Definition | Current UAH Policy | Recommendation to ensure UG Compliance |
|
The Federal government's preferred procurement method for construction (when certain conditions apply) and for goods/services where price will be the main consideration for selecting the winning bidder. If sealed bids are used, the guidance outlines five explicit requirements to follow including:
|
|
|
Complex Acquisitions: Competitive Proposals
| Complex Acquisitions: Competitive Proposals | Definition | Current UAH Policy | Recommendation to ensure UG Compliance |
|
The Competitive Proposal Method is used when there are critical factors to consider beyond just price. Both fixed-price and cost-reimbursement type contracts can be used and certain general requirements must be followed including:
|
|
|
Non-Competitive Proposals/Sole Source
| Non-Competitive Proposals | Definition | Current UAH Policy | Recommendation to ensure UG Compliance |
|
The non-competitive proposal also called a "no-bid" contract or sole-source procurement applies in very specific situations that eliminate the need for competition in the solicitation process.
Non-competitive proposals apply to any procurement greater than $10,000 and are used when there is adequate "justification for other than full and open competition".
This can occur when one or more of the following are met:
|
|
|
|
FAQs Complex Acquisitions--Competitive Proposal Process |
|